West 58th Street Reconstruction

Share on Facebook Share on Twitter Share on Linkedin Email this link
The 58th Street Reconstruction project will be between Wooddale Ave and Xerxes Ave.

The West 58th Street portion of the project includes complete reconstruction of the roadway pavement, full installation of concrete curb and gutter, partial replacement of watermain and full replacement of water services, improvements to the sanitary sewer and storm sewer systems, traffic signal replacement at France Avenue, and construction of a 5-foot concrete sidewalk on the north side and an 6-foot concrete concrete sidewalk on the south side.

The France Avenue portion of the project between West 58th Street and Minnehaha Creek includes partial reconstruction of the roadway pavement, partial replacement of concrete curb and gutter, full replacement of watermain and water services, improvements to the storm sewer system, traffic signal replacement at West 58th Street, and construction of a 5-foot concrete sidewalk on the east side of France Avenue between West 57th and West 58th Sts.

The West 58th Street portion of the project includes complete reconstruction of the roadway pavement, full installation of concrete curb and gutter, partial replacement of watermain and full replacement of water services, improvements to the sanitary sewer and storm sewer systems, traffic signal replacement at France Avenue, and construction of a 5-foot concrete sidewalk on the north side and an 6-foot concrete concrete sidewalk on the south side.

The France Avenue portion of the project between West 58th Street and Minnehaha Creek includes partial reconstruction of the roadway pavement, partial replacement of concrete curb and gutter, full replacement of watermain and water services, improvements to the storm sewer system, traffic signal replacement at West 58th Street, and construction of a 5-foot concrete sidewalk on the east side of France Avenue between West 57th and West 58th Sts.

  • Construction Update - 7/2/2020

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    5 days ago

    • Watermain installation continued between France Avenue and Xerxes Avenue and will continue through next week.
    • Topsoil was removed from Wooddale Avenue to France Avenue this week. Crews will continue with roadway grading in this area next week.
    • Watermain shutdown on Tuesday July 7th will affect residents on Abbott Avenue from West 56th Street to West 60th Street. This shutdown will allow City of Edina crews to make a watermain repair at West 57th Street and Abbott Avenue. Please continue to check your front door for any time sensitive notices.

    Have a wonderful and safe 4th of July Weekend.

    • Watermain installation continued between France Avenue and Xerxes Avenue and will continue through next week.
    • Topsoil was removed from Wooddale Avenue to France Avenue this week. Crews will continue with roadway grading in this area next week.
    • Watermain shutdown on Tuesday July 7th will affect residents on Abbott Avenue from West 56th Street to West 60th Street. This shutdown will allow City of Edina crews to make a watermain repair at West 57th Street and Abbott Avenue. Please continue to check your front door for any time sensitive notices.

    Have a wonderful and safe 4th of July Weekend.

  • Construction Update - 6/26/2020

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    11 days ago

    • Next week crews will begin watermain work from France Avenue to Xerxes Avenue. Please watch your front doors for water shutoff notices.
    • CenterPoint Energy continued the removal of the old gas main between France Avenue and Xerxes Avenue.
    • Crews completed the storm sewer installation between Wooddale Avenue and France Avenue.
    • Roadway and sidewalk grading began with the removal of topsoil. This work started at France Avenue and will progress to the west towards Wooddale Avenue.

    • Next week crews will begin watermain work from France Avenue to Xerxes Avenue. Please watch your front doors for water shutoff notices.
    • CenterPoint Energy continued the removal of the old gas main between France Avenue and Xerxes Avenue.
    • Crews completed the storm sewer installation between Wooddale Avenue and France Avenue.
    • Roadway and sidewalk grading began with the removal of topsoil. This work started at France Avenue and will progress to the west towards Wooddale Avenue.
  • Construction Update - 6/19/2020

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    18 days ago

    • Hennepin County seal coated France Avenue and added new striping. See the following link for details on the new striping configuration. https://www.bettertogetheredina.org/france-ave-safety-improvements
    • France Avenue speed limit has been temporarily reduced to 25 mph from W 56th Street to West 60th Street during construction.
    • CenterPoint Energy / Michels completed gas main removal from Wooddale Avenue to France Avenue.
    • CenterPoint Energy / Michels plans to begin gas main removal from France Avenue to Xerxes Avenue on Wednesday, June 24.
    • Crews started storm sewer installation which will continue next week.

    • Hennepin County seal coated France Avenue and added new striping. See the following link for details on the new striping configuration. https://www.bettertogetheredina.org/france-ave-safety-improvements
    • France Avenue speed limit has been temporarily reduced to 25 mph from W 56th Street to West 60th Street during construction.
    • CenterPoint Energy / Michels completed gas main removal from Wooddale Avenue to France Avenue.
    • CenterPoint Energy / Michels plans to begin gas main removal from France Avenue to Xerxes Avenue on Wednesday, June 24.
    • Crews started storm sewer installation which will continue next week.
  • Construction Update - 6/12/2020

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    25 days ago

    • Traffic Control Changes
      • West 58th Street from Wooddale Avenue to Xerxes Avenue will be closed to all non-local traffic beginning on Monday, June 15th. Residents with driveways off of West 58th Street will continue to have access.
      • All cross streets east of France Avenue will also be closed to through traffic.
      • The France Avenue traffic signal will be removed on Monday, June 15th. There will be no access to France Avenue from West 58th Street. The new traffic signal will be installed later in the project.
      • Residents on Brookview Avenue and west of Philbrook Avenue will continue to access their homes using Oaklawn Avenue through Tuesday, June 16th.
    • CenterPoint Energy began removal of the abandoned gas main. Crews anticipate the full removal from Wooddale Avenue to Xerxes Avenue to take around 2 weeks.
    • Watermain installation began between France Avenue and Xerxes Avenue. The pipe will continue to be installed next week, and connections to the existing watermain will occur at a later date.
    • Pavement reclamation of West 58th Street from France Avenue to Xerxes Avenue will occur on Saturday, June 13th.
    • Crews will begin the storm sewer installation on Monday between Wooddale and Kellogg Avenue and then transition to install a new sanitary manhole between Philbrook Lane and Brookview Avenue on Tuesday.

    • Traffic Control Changes
      • West 58th Street from Wooddale Avenue to Xerxes Avenue will be closed to all non-local traffic beginning on Monday, June 15th. Residents with driveways off of West 58th Street will continue to have access.
      • All cross streets east of France Avenue will also be closed to through traffic.
      • The France Avenue traffic signal will be removed on Monday, June 15th. There will be no access to France Avenue from West 58th Street. The new traffic signal will be installed later in the project.
      • Residents on Brookview Avenue and west of Philbrook Avenue will continue to access their homes using Oaklawn Avenue through Tuesday, June 16th.
    • CenterPoint Energy began removal of the abandoned gas main. Crews anticipate the full removal from Wooddale Avenue to Xerxes Avenue to take around 2 weeks.
    • Watermain installation began between France Avenue and Xerxes Avenue. The pipe will continue to be installed next week, and connections to the existing watermain will occur at a later date.
    • Pavement reclamation of West 58th Street from France Avenue to Xerxes Avenue will occur on Saturday, June 13th.
    • Crews will begin the storm sewer installation on Monday between Wooddale and Kellogg Avenue and then transition to install a new sanitary manhole between Philbrook Lane and Brookview Avenue on Tuesday.
  • Construction Update - 6/5/2020

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    about 1 month ago

    The project has been delayed until CenterPoint Energy can complete their gas main replacement. Park Construction anticipates resuming work on Monday, June 15, 2020.

    The project has been delayed until CenterPoint Energy can complete their gas main replacement. Park Construction anticipates resuming work on Monday, June 15, 2020.

  • Construction Update - 5/30/2020

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    about 1 month ago

    • CenterPoint Energy completed the gas main installation between France Avenue and Xerxes Avenue and will continue with service installations along that portion.
    • Crews reclaimed West 58th Street between Wooddale Avenue and France Avenue. This process took the paved roadway from a blacktop road to a gravel road.
    • Crews will be in the week of June 1st to begin installing the new watermain between France Avenue and Xerxes Avenue. No water shutdowns are planned for this work.
    • Crews will also begin the removal and installation of a sanitary manhole between Philbrook Lane and Brookview Avenue. This work is expected to take a few days.

    Detour Update (Temporary)

    • All residents to the west of Philbrook Lane, including Brookview Avenue, will access their homes from Oaklawn Avenue starting on Wednesday, June 3.

    Please drive slow through the construction site to keep the dust down. Crews will regularly water the road surface to minimize the amount of dust.

    Thank you for your cooperation and patience. Have a wonderful week.

    • CenterPoint Energy completed the gas main installation between France Avenue and Xerxes Avenue and will continue with service installations along that portion.
    • Crews reclaimed West 58th Street between Wooddale Avenue and France Avenue. This process took the paved roadway from a blacktop road to a gravel road.
    • Crews will be in the week of June 1st to begin installing the new watermain between France Avenue and Xerxes Avenue. No water shutdowns are planned for this work.
    • Crews will also begin the removal and installation of a sanitary manhole between Philbrook Lane and Brookview Avenue. This work is expected to take a few days.

    Detour Update (Temporary)

    • All residents to the west of Philbrook Lane, including Brookview Avenue, will access their homes from Oaklawn Avenue starting on Wednesday, June 3.

    Please drive slow through the construction site to keep the dust down. Crews will regularly water the road surface to minimize the amount of dust.

    Thank you for your cooperation and patience. Have a wonderful week.

  • Construction Update - 5/15/20

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    about 2 months ago

    • CenterPoint Energy crews continue to install the new gas main between France Avenue and Xerxes Avenue. Service crews began installing the new gas services between Wooddale Avenue and France Avenue.
    • Please contact CenterPoint Energy with any questions or concerns.
    • The final layer of asphalt was installed on the south parking lot of Pamela Park. Restoration and striping is tentatively scheduled for next week.
    • Watermain and sewer upgrades continue between Wooddale Avenue and France Avenue. This process will involve flushing of the main which may stir up mineral deposits. This can cause the water to appear cloudy but the water is...

    • CenterPoint Energy crews continue to install the new gas main between France Avenue and Xerxes Avenue. Service crews began installing the new gas services between Wooddale Avenue and France Avenue.
    • Please contact CenterPoint Energy with any questions or concerns.
    • The final layer of asphalt was installed on the south parking lot of Pamela Park. Restoration and striping is tentatively scheduled for next week.
    • Watermain and sewer upgrades continue between Wooddale Avenue and France Avenue. This process will involve flushing of the main which may stir up mineral deposits. This can cause the water to appear cloudy but the water is still safe to drink. Simply run your water faucet about 1/4 turn open in a laundry room sink or tub for a few minutes to clear the water up.

    Thank you for patience during this project. Have a great weekend.

  • Construction Update - 5/8/20

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    2 months ago

    • CenterPoint Energy completed the gas main installation between Wooddale and France Aves. Service crews will begin service line work within the couple weeks.
    • CenterPoint Energy began gas main installation between France and Xerxes Aves. This work will continue over the next couple weeks.
    • Please contact CenterPoint Energy with any questions or concerns.
    • The first layer of asphalt was installed in the south lot of Pamela Park. Next week restoration will occur followed by the final asphalt layer. Striping will be installed a few days after paving is complete.
    • Watermain upgrades continue to occur between France and Wooddale Aves. Please check...

    • CenterPoint Energy completed the gas main installation between Wooddale and France Aves. Service crews will begin service line work within the couple weeks.
    • CenterPoint Energy began gas main installation between France and Xerxes Aves. This work will continue over the next couple weeks.
    • Please contact CenterPoint Energy with any questions or concerns.
    • The first layer of asphalt was installed in the south lot of Pamela Park. Next week restoration will occur followed by the final asphalt layer. Striping will be installed a few days after paving is complete.
    • Watermain upgrades continue to occur between France and Wooddale Aves. Please check your doors for water shutoff notices.

    Thank you for your patience and have a wonderful Mothers Day, a safe Minnesota fishing opener and Stay Well.


  • Construction Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    2 months ago



  • Construction Kickoff

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    2 months ago



    You need to be signed in to add your comment.

    comment
    Submitting your comment
    Cancel