Construction Update - 7/24/2020

11 days ago

  • Crews completed the major grading work from Wooddale Avenue to France Avenue. Fine grading in preparation for curb will occur at the beginning of next week.
  • Concrete driveways, curb and gutter, and aprons are scheduled to be installed towards the end of next week. Watch you front doors for notices on driveway access restrictions. After concrete is poured, please do not drive across it for 5-7 days, as it needs time to gain sufficient strength.
  • Crews continue to work on the storm sewer installation between France Avenue and Xerxes Avenue. This work will continue for the next couple weeks.
  • France Avenue will be reopened by the end of the day on Friday, July 24th.