Night work and road closure - schedule update 5/12
5/12 - This post was updated, the schedule was moved back 1 day to Tuesday-Thursday.
The contractors will begin work on relining the existing storm sewer pipe on Tuesday, 5/13. As part of this work, road closures will be required at the following dates and times:
• Tuesday, 5/13: 2-hour road closure around 9-11 am for crane set up
• Wednesday, 5/14: 5-8-hour road closure around 9 am-5 pm for crane work on the liner
• Wednesday night: Overnight work with high engine idle noise levels and crew on site with lights
• Thursday, 5/14: 2-hour road closure around 9-11 am for take down of crane
Please consider parking your vehicle on Brook Drive between Limerick Ln and Hillside Ln if you anticipate needing vehicle access on these days, especially on Tuesday. Thank you for your patience as we wrap up this project.