Preliminary Construction Schedule

The contractor has shared the probable schedule. The current production schedule of the box culvert has delivery on 10/15/24. The probable road closure window is October 15 to October 25, with the possibility to shift earlier or later by 1 week.

The early work will include removal of the road and bypass of the sanitary sewer. The main work will include placement of the box culvert and storm sewer. The later work will include road base and road.