Schedule for week of 4/28, 5/5, 5/12
The week of 4/21 we are seeing storm manhole, curb and driveway concrete installed.
Week of 4/28 schedule includes;
- Grading
- Topsoil
- Blacktop driveway
Week of 5/5 we are scheduled to see
- Sawcutting and Blacktop patching
- Sign install
- Irrigation repair
- Possible this week include- Tree planting
- guard rail install
- Final paving
 
Week of 5/12
- Storm Sewer Lining- We are working with the contractor to understand the impacts of this activity to traffic and nighttime work and will provide more details in a separate post
 