Storm sewer lining - night work and road closures

As a result of our design change last year caused by the gas company's delay, we choose to install a lining pipe inside the existing concrete sewer pipe. This work is tentatively schedule for the week of 5/12 and needs 72 hours without rain in the forecast.

The following interruptions are expected as part of this work.

  • Day 1: Approximately 2 hour road closure around 9-11am for set up of tower with crane
  • Day 2: Approximately 5-8 hour road closure around 9am-5pm for crane work for liner
  • Night of Day 2: Overnight work with high engine idle noise levels and crew on site with lights
  • Day 3: Approximately 2 hour road closure around 9-11am for take down of tower with crane

We'll go door to door to the closest neighbors and those without road access and update this message with details as the schedule develops.