Winter wrap up, spring planning
As we close out for the winter, here are the issues we're closing and those that will wait until the Spring;
Closed out
- Culvert, utilities, and road base
- Soil filled rock riprap
- Seeding and erosion control blanket is in place
- Temporary barriers and marking at creek crossing
- Base
- Temporary pavement on the road and at 3 driveways
Still to close
- Street light repair (working with Xcel)
Spring list
- Manhole grouting & pipe lining or manhole replacement and new 48"
pipe - Sign installation
- Curb, 2nd layer of pavement
- Remove temporary barriers and install guard rail
- Minor restoration, minor yard / rut repair
- Tree planting
- Irrigation repair
Please review the list and let us know if you are seeing anything else that might be missing.
Share Winter wrap up, spring planning on Facebook
Share Winter wrap up, spring planning on Twitter
Share Winter wrap up, spring planning on Linkedin
Email Winter wrap up, spring planning link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends