Construction Update - 4/26/24
As construction begins in your phase, we would like to stress the importance of checking your front door daily for time sensitive notifications.
Phase 1: Concord Ave, W 64th St, Millers Ln, and Rose Ct
- Removals including curb and gutter, driveways, and landscaping will continue into the week of 4/29. A select number of trees will be removed as well.
- Utility work on Millers Ln, Rose Ct and W. 64th St. will continue into the week of 4/29.
- Setup of the temporary above ground water main is complete.
- Bituminous Roadways will be reaching out to Concord Ave residents to set up temporary water service. They will need access to the home by 5/3 to finalize the transition to the temporary watermain.
- Watermain work on Concord Ave is scheduled to begin on 5/6.
- Storm sewer work on W. 64th St will occur the week of 4/29.
- Check your front door daily for notification of temporary driveway access or water loss.
Phase 2: W. 63rd St, Ashcroft Ln, Garrison Ln, Nancy Ln, St. Johns Ave south of Garrison Ln, and Wooddale Ave – Work tentatively scheduled to begin early July
- A select number of trees will be removed in concurrence with Phase 1 tree removals.
Phase 3: W. 62nd St, Ashcroft Ave, St Johns Ave north of Garrison Ln, and Virginia Ln – Work tentatively scheduled to begin early August
- A select number of trees will be removed in concurrence with Phase 1 tree removals.
Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.