Construction Update - 5/10/2024
As construction begins in your phase, PLEASE consistently check your front door daily for time sensitive notifications.
Phase 1: W 64th St, Millers Ln, and Rose Ct
- Curb and gutter installation is scheduled for the week of 5/13 pending weather conditions.
- Watermain work is now complete.
- Check your front door daily for notification of temporary driveway access loss.
Phase 1: Concord Ave
- Removals including curb and gutter, driveways, and landscaping will continue into the week of 5/13. A select number of trees will be removed as well.
- Temporary above ground water main setup is complete.
- Watermain work will continue into the week of 5/13.
- Check your front door daily for notification of temporary driveway access or water loss.
Phase 2: W. 63rd St, Ashcroft Ln, Garrison Ln, Nancy Ln, St. Johns Ave south of Garrison Ln, and Wooddale Ave – Work tentatively scheduled to begin early July.
- A select number of trees will be removed in concurrence with Phase 1 tree removals.
Phase 3: W. 62nd St, Ashcroft Ave, St Johns Ave north of Garrison Ln, and Virginia Ln – Work tentatively scheduled to begin early August.
- A select number of trees will be removed in concurrence with Phase 1 tree removals.
Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.