Construction Update - 5/17/2024
As construction begins in your phase, PLEASE consistently check your front door daily for time sensitive notifications.
Phase 1: W 64th St, Millers Ln, and Rose Ct
- Curb and driveway apron installation is complete.
- Access will be restored to driveways the week of 5/20 once the new concrete has cured.
- The first layer of asphalt will be paved the week of 5/20 pending weather conditions.
- A select number of trees will be removed or trimmed on the south side of W 64th St for the installation of the new sidewalk.
Phase 1: Concord Ave
- Watermain and hydrant installations are complete.
- Water service installation will continue into the week of 5/20.
- Temporary above ground water will be removed from homes as water services are completed.
- Check your front door daily for notification of temporary driveway access or water loss.
- Roadway work will begin at Concord/64th St the week of 5/20.
Phase 2: Ashcroft Ln
- Driveway removals for temporary water installation will begin the week of 5/20.
- A select number of trees will be removed in concurrence with Phase 1 tree removals.
Phase 2: W. 63rd St, Ashcroft Ln, Garrison Ln, Nancy Ln, St. Johns Ave south of Garrison Ln, and Wooddale Ave – Work tentatively scheduled to begin early July.
- A select number of trees will be removed in concurrence with Phase 1 tree removals.
Phase 3: W. 62nd St, Ashcroft Ave, St Johns Ave north of Garrison Ln, and Virginia Ln – Work tentatively scheduled to begin early August.
- A select number of trees will be removed in concurrence with Phase 1 tree removals.
Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.