Construction Update - 6/14/2024

As construction begins in your phase, PLEASE consistently check your front door daily for time sensitive notifications. All of the updates below are weather permitting.


Phase 1: W 64th St, Millers Ln, and Rose Ct

  • Irrigation repairs are scheduled to begin the week of 6/17.
  • Weather permitting, excavation in preparation for topsoil installation will continue into the week of 6/17.
  • Weather permitting, sidewalk installation on W 64th St is scheduled for the week of 6/17.


Phase 1: Concord Ave

  • Sump line installation on Concord Ave is complete.
  • Curb and gutter notifications will likely be sent out on Monday 6/17. Weather permitting, curb will begin the week of 6/17.
  • Check your front door daily for notification of temporary driveway access or water loss.


Phase 2: Ashcroft Ln

  • Water main installation is complete.
  • Water service installations will continue into the week of 6/17.
  • Sump line installation will continue into the week of 6/17.
  • Check your front door daily for notification of temporary driveway access or water loss.


Phase 2: St. Johns Ave south of Garrison Ln

  • Temporary water lines have now been installed.
  • Road removals for the installation of the new water main are complete.
  • Water main installation will begin the week of 6/17.
  • Check your front door daily for notification of temporary driveway access or water loss.


Phase 2: W. 63rd St, Garrison Ln, Nancy Ln, St. Johns Ave south of Garrison Ln, and Wooddale Ave – Work tentatively scheduled to begin early July.

  • Temporary above ground water lines have been installed in preparation for the upcoming water main installation.
  • Check your front door daily for notification of temporary driveway access or water loss.


Phase 3: W. 62nd St, Ashcroft Ave, St Johns Ave north of Garrison Ln, and Virginia Ln – Work tentatively scheduled to begin early August.


Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.