Construction Update- 6/21/2024
As construction begins in your phase, PLEASE consistently check your front door daily for time sensitive notifications. All updates below are scheduled for the week of 6/24 and are WEATHER PERMITTING.
W 64th St, Millers Ln, and Rose Ct
- Irrigation repairs will continue. The contractor will be reaching out to coordinate with homeowners.
- Excavation in preparation for topsoil installation will continue following completion of irrigation repairs.
- Sidewalk installation on W 64th St. has been tentatively rescheduled for the week of 6/24.
Concord Ave
- Curb and gutter installation has been tentatively rescheduled for the week of 6/24.
- Roadway excavation and gravel installation from W. 63rd to 64th St. will begin on 6/24.
- Check your front door daily for notification of temporary driveway access or water loss.
Ashcroft Ln
- Water service installation work will continue this week.
- Check your front door daily for notification of temporary driveway access or water loss.
St. Johns Ave south of Garrison Ln
- Water main installation is complete.
- Water service installation work will begin this week.
- Check your front door daily for notification of temporary driveway access or water loss.
W. 63rd St, Garrison Ln, Nancy Ln, and Wooddale Ave – Work tentatively scheduled to begin early July.
- Temporary above ground water lines have been installed in preparation for the upcoming water main installation.
- Check your front door daily for notification of temporary driveway access or water loss.
W. 62nd St, Ashcroft Ave, St Johns Ave north of Garrison Ln, and Virginia Ln – Work tentatively scheduled to begin early August.
Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.