Construction Update- 6/28/2024

As construction begins on your street, PLEASE consistently check your front door daily for time sensitive notifications. All updates below are scheduled for the week of 7/1 and are WEATHER PERMITTING.
Crews will not be working onsite Thursday, 7/4 or Friday, 7/5. Happy 4th of July!
Traffic Update
- Expect delays driving on Concord Avenue during concrete installation. We recommend using alternate routes during the week.
- A map visualizing this traffic update can be found here.
W 64th St, Millers Ln, and Rose Ct
- Irrigation repairs began. If your system has not been repaired, please reach out to Brandon Freeman.
- Excavation in preparation for topsoil installation will continue following completion of irrigation repairs.
- Concrete sidewalk installation on W 64th St. has been tentatively rescheduled for the week of 7/1.
Concord Ave
- Concrete curb and gutter installation, closely followed by concrete driveway installations has been tentatively rescheduled for Monday, 7/1. This work is tentatively scheduled to be completed by Wednesday, 7/3.
- Check your front door daily for notification of temporary driveway access or water loss.
Ashcroft Ln
- Water service installation work will continue the week of 7/1.
- Check your front door daily for notification of temporary driveway access or water loss.
St. Johns Ave south of Garrison Ln
- Water service installation is scheduled to begin the week of 7/8.
- Check your front door daily for notification of temporary driveway access or water loss.
W. 63rd St, Garrison Ln, Nancy Ln, and Wooddale Ave – Work tentatively scheduled to begin early July.
- Temporary above ground water lines have been installed in preparation for the upcoming water main installation.
- Check your front door daily for notification of temporary driveway access or water loss.
W. 62nd St, Ashcroft Ave, St Johns Ave north of Garrison Ln, and Virginia Ln – Work tentatively scheduled to begin early August.
Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.