Construction Update - 7/12/2024
As construction begins on your street, PLEASE consistently check your front door daily for time sensitive notifications. All updates below are scheduled for the week of 7/15 and are WEATHER PERMITTING.
Traffic Update
- Expect closures and delays near the intersection of St. Johns/ Garrison Ln. We recommend using alternate routes during the week.
- A map visualizing this traffic update can be found here.
W 64th St, Millers Ln, and Rose Ct
- Concrete sidewalk installation on W 64th St. is tentatively scheduled for 7/18.
- Excavation in preparation for topsoil is occurring sporadically.
Concord Ave
- Concrete curb and gutter installation is complete.
- Concrete sidewalk installation is tentatively scheduled for 7/18.
- The first layer of asphalt paving is complete. Please continue to park vehicles in driveways or on adjacent streets to prevent construction interruptions.
- Asphalt driveway restoration paving is scheduled for 7/19.
- Check your front door daily for notification of temporary driveway access or water loss.
Ashcroft Ln
- Removal of the remaining concrete on the west side of the roadway.
- Removal and replacement of poor soils in preparation for curb and gutter.
- Water service installation is complete.
- Temporary water has been removed.
- Check your front door daily for notification of temporary driveway access or water loss.
St. Johns Ave south of Garrison Ln
- Removal of temporary water service from homes.
- Sump line installation from W64th St to Garrison Ln.
- Storm sewer will be installed on Monday, 7/15 and Tuesday, 7/16 at the intersection of St. Johns Ave / Garrison Ln. Please use alternate routes if traveling in this area.
- Water service installation is complete.
- Check your front door daily for notification of temporary driveway access or water loss.
W. 63rd St, Garrison Ln, Nancy Ln, and Wooddale Ave – Work tentatively scheduled to begin early July.
- Temporary above ground water lines have been installed in preparation for the upcoming water main installation.
- Bituminous Roadways will be reaching out to coordinate hooking up the temporary water line to homes the week of 7/15.
- Storm sewer will be installed on Monday, 7/15 and Tuesday, 7/16 at the intersection of St. Johns Ave / Garrison Ln. Please use alternate routes if traveling in this area.
- Check your front door daily for notification of temporary driveway access or water loss.
W. 62nd St, Ashcroft Ave, St Johns Ave north of Garrison Ln, and Virginia Ln – Work tentatively scheduled to begin early August.
Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
