Construction Update - 7/19/2024
As construction begins on your street, PLEASE consistently check your front door daily for time sensitive notifications. All updates below are scheduled for the week of 7/22 and are WEATHER PERMITTING.
Traffic Update
- The intersection of Wooddale Ave and Valley View Road will be closed for the week of 7/22. Please use alternative routes.
- A map visualizing this traffic update can be found here.
W 64th St, Millers Ln, and Rose Ct
- Excavation in preparation for topsoil is occurring sporadically.
- Concrete sidewalk and pedestrian ramp installation on W 64th St. has been tentatively scheduled for 7/25.
Concord Ave
- Concrete sidewalk installation is tentatively scheduled for Thursday 7/25 and Friday 7/26.
- Please continue to park vehicles in driveways or on adjacent streets to prevent construction interruptions.
- Check your front door daily for notification of temporary driveway access or water loss.
Ashcroft Ln
- Removal and replacement of poor soils in preparation for curb and gutter will continue between West 63rd and 64th Sts.
- Completing storm sewer installation at the intersection of Ashcroft Ln and St Johns Ave.
- Check your front door daily for notification of temporary driveway access or water loss.
St. Johns Ave south of Garrison Ln
- Removal of the remaining concrete on the west side of the street, followed by the removal and replacement of poor soils in preparation for curb and gutter.
- Removal of temporary water service from homes is scheduled to be complete by 7/26.
- Check your front door daily for notification of temporary driveway access or water loss.
W. 63rd St, Garrison Ln, Nancy Ln, and Wooddale Ave
- Installation of the new water main.
- Check your front door daily for notification of temporary driveway access or water loss.
Virginia Ln
- Removal and replacement of poor soils in preparation for curb and gutter.
W. 62nd St, Ashcroft Ave, St Johns Ave north of Garrison Ln – Work tentatively scheduled to begin early August.
Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.