Construction Update - 7/26/2024

As construction begins on your street, PLEASE consistently check your front door daily for time sensitive notifications. All updates below are scheduled for the week of 7/29 and are WEATHER PERMITTING.


Traffic Update

  • The intersection of Wooddale Ave / Valley View Road will be closed on 7/29 through 7/30. Please use alternative routes.
  • A map visualizing this traffic update can be found here.


W 64th St, Millers Ln, and Rose Ct

  • Excavation in preparation for topsoil is occurring sporadically.
  • Curb and sidewalk installation west of St. Johns Ave.


Concord Ave

  • Excavation in preparation for topsoil and retaining walls is occurring sporadically.
  • Irrigation repairs will begin.
  • Please continue to park vehicles in driveways or on adjacent streets to prevent construction interruptions.
  • Check your front door daily for notification of temporary driveway access or water loss.


Ashcroft Ln

  • Removal and replacement of poor soils in preparation for curb and gutter will continue between West 63rd St and St. Johns Ave.
  • Storm sewer installation at the intersection of Ashcroft Ln and St Johns Ave.
  • Installation of curb and gutter followed by concrete driveway restoration is tentatively scheduled to begin on Wednesday, 7/31.
  • Check your front door daily for notification of temporary driveway access or water loss.


St. Johns Ave south of Garrison Ln

  • Removal of the remaining concrete on the west side of the street, followed by the removal and replacement of poor soils in preparation for curb and gutter.
  • Installation of curb and gutter followed by concrete driveway replacements is tentatively scheduled to begin on Wednesday, 7/31.
  • Check your front door daily for notification of temporary driveway access or water loss.


W. 63rd St

  • Installation of curb and gutter followed by driveway replacements is tentatively scheduled to begin on Wednesday, 7/31.


Garrison Ln, Nancy Ln, and Wooddale Ave

  • Installation of the new water main and water services will continue.
  • Check your front door daily for notification of temporary driveway access or water loss.


Virginia Ln

  • Installation of curb and gutter followed by driveway replacements is tentatively scheduled to begin on Wednesday, 7/31.


W. 62nd St, Ashcroft Ave, St Johns Ave north of Garrison Ln

  • Temporary water will begin to be setup in preparation for water main replacement.


Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.