Construction Update - 9/6/2024
PLEASE consistently check your front door daily for time sensitive notifications. All updates below are scheduled for the week of 9/9 and are WEATHER PERMITTING.
Concord Ave, Ashcroft Ln, W. 63rd St, St. Johns Ave (South of Garrison Ln), Virginia Ln, W 64th St, Millers Ln, Rose Ct, Garrison Ln, Nancy Ln
- Boulevard excavation and topsoil installation are occurring sporadically.
- Retaining wall installation began.
- Sign installation.
- Dave’s Irrigation will continue doing irrigation repairs throughout the project.
- Please continue to park vehicles in driveways to prevent construction interruptions.
- Check your front door daily for notification of temporary driveway access or water loss.
Wooddale Ave
- Excavation in preparation for sidewalk installation on Wooddale Ave.
- Boulevard excavation and topsoil installation are occurring sporadically.
- Check your front door daily for notification of temporary driveway access or water loss.
W. 62nd St, Ashcroft Ave, St. Johns Ave (North of Garrison Ln)
- Reclaiming of the remaining asphalt on W 62nd St and Ashcroft Ave will take place on Saturday, 9/7. Please have all vehicles off the road before 7:00 am or you may get towed.
- Temporary water is being removed from homes. If you have not contacted Bituminous Roadways, please reach out to Jake Evertz at 651-600-9120 by Monday, 9/9 to avoid interruption.
- Storm sewer installation on St. Johns Ave and Ashcroft Ave.
- Removal and replacement of poor soils in preparation for curb and gutter.
- Check your front door daily for notification of temporary driveway access or water loss.
Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Share Construction Update - 9/6/2024 on Facebook
Share Construction Update - 9/6/2024 on Twitter
Share Construction Update - 9/6/2024 on Linkedin
Email Construction Update - 9/6/2024 link