Construction Kickoff-Phase 1 set to begin 6/21

Construction is scheduled to begin on 6/21. The following construction activities are scheduled to occur during the week of 6/21 in Phase 1.

  • Asphalt pavement reclamation.
    • This process grinds up the pavement and gravel underneath the road to produce a suitable recycled material to use as a temporary driving surface.
  • Installation of an above ground temporary water supply system on Beard Ave from Beard Ct to Fuller St and on W 55th St from France Ave to Ewing Ave.
    • This will allow the contractor to replace the existing watermain and services with minimal disruption to your water supply.
    • The contractor will need access to your basement to finalize the setup.
    • The contractor will be contacting you with a knock on the door or a notification on your door to set up temporary water service.
    • Please check your front door frequently for time sensitive notices.
    • The watermain repairs and water service installation is scheduled to finish mid-July, weather permitting.
  • Tree removal at select locations
  • Utility improvements

Parking restrictions are in effect for Phase 1. There is No Parking from the hours of 7 AM to 9 PM or until the contractor has noticeably left for the day.

We look forward to working with you throughout this important construction project.