Construction Update 10/15/2021

Phase 1 (West 55th Street, Beard Avenue (south half), Beard Court, Drew Avenue (south half) and Ewing Circle

  • A majority of irrigation system repairs are complete. The contractor will repair the remaining few this fall.
  • Seeding and hydromulching is complete. See the post titled "Tips for Growing Green Grass" or watch the video titled "Growing Green Grass" for reference information on your new seeded lawn.


Phase 2 (West 54th Street, Abbott Place, Beard Avenue (north half), Drew Avenue (north half) and Fuller Street.

  • Concrete curb installation is complete.
  • Driveway apron installation began on 10/14 and it is expected to continue during the week of 10/18. Expect limited roadway access during this period and no driveway access for at least 5 days as the concrete gains sufficient strength.
  • Boulevard excavation in preparation of topsoil and sidewalk installation is expected to begin during the week of 10/18.
  • The first layer of asphalt paving is anticipated to occur during the week of 10/25.

US Internet

US Internet plans to install fiber optic lines in the City right of way later in October. More details can be found here.


Parking restrictions remain in effect for Phase 1 and 2. There is No Parking from the hours of 7 AM to 9 PM or until the contractor has noticeably left for the day. Please remember these schedules are weather-dependent and are subject to change