Construction Update 11/05/2021
Phase 1 and 2
- The final layer of asphalt paving will be complete on 11/5.
- All the landscaping plantings will occur in the spring of 2022.
- A majority of the irrigation system repairs are complete. The contractor will test and repair the remaining few in the spring of 2022.
Phase 2 (West 54th Street, Abbott Place, Beard Avenue (north half), Drew Avenue (north half) and Fuller Street.
- The City of Minneapolis will be paving the final 2 inch layer of asphalt on both sides of West 54th Street on Saturday, 11/6. During this work West 54th Street will be closed between France Avenue and Zenith Avenue from 7 AM to 6 PM. France Avenue can be accessed via West 53rd Street or Fuller Street.
- Boulevard excavation and topsoil installation is complete.
- Dormant seeding is complete. Hydromulch placement will occur the week of 11/8.
- The anticipated schedule is weather-dependent and is subject to change.
US Internet
- US Internet fiber optic installation in the City right of way is complete.
- US Internet will restore turf impacted by their fiber optic installation.
Share Construction Update 11/05/2021 on Facebook
Share Construction Update 11/05/2021 on Twitter
Share Construction Update 11/05/2021 on Linkedin
Email Construction Update 11/05/2021 link
Consultation has concluded