Construction Update 8/13/2021

Phase 1

  • The contractor anticipates backfilling the utility trench at W 55th St and Beard Ave intersection on 8/13.
  • Roadway excavation is scheduled to begin during the week of 8/16. The contractor will remove at least 1 foot of soil below the current road surface for the full width of the street to install the gravel base and confirm the soils are stable enough to support vehicular traffic. During this work, you can expect periodic loss of access to your driveways for up to an hour. If you need immediate access, please wave to one of the contractors to get their attention and they can accommodate.
  • Storm sewer installation and water service replacements are scheduled to continue during the week of 8/16. Expect water shutoff and limited access to some roads and driveways for short periods. The contractor will knock on your front door to notify you of the temporary water shutoff and driveway access restrictions.
  • The watermain system improvements are scheduled to be complete on 8/20, weather permitting.


Parking restrictions will be in effect for Phase 1. There is No Parking from the hours of 7 AM to 9 PM or until the contractor has noticeably left for the day.

Share Construction Update 8/13/2021 on Facebook Share Construction Update 8/13/2021 on Twitter Share Construction Update 8/13/2021 on Linkedin Email Construction Update 8/13/2021 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>