Construction Update 8/27/2021
See the Assessment Update for Creek Knoll here.
Phase 1
- Curb and gutter installation is complete.
- Installation of concrete aprons and driveways is scheduled to begin during the week of 8/30, weather permitting. As the notice delivered to your door states, expect loss of access to your driveways for 5 days while the concrete gains strength.
- Sanitary sewer lining is scheduled to begin. See the link for details.
- The first layer of asphalt paving is scheduled to occur during the week of 9/6.
- Parking restrictions will be in effect for Phase 1. There is No Parking from the hours of 7 AM to 9 PM or until the contractor has noticeably left for the day.
Phase 2
- The contractor anticipates work beginning the week of 9/6, weather permitting.