Construction Update 9/16/2021

Phase 1 (West 55th Street, Beard Avenue (south half), Beard Court, Drew Avenue (south half) and Ewing Circle

  • Asphalt driveway paving is complete.
  • Watermain improvements on W. 55th St adjacent to the France Ave intersection are complete.
  • Preparing the boulevards for topsoil placement, including removing debris and soils to a 6" depth, and any grading required to blend the boulevards into the curb is rescheduled to the week of 9/20.
  • Irrigation system repairs are anticipated to start the week of 9/20.


Phase 2 (West 54th Street, Abbott Place, Beard Avenue (north half), Drew Avenue (north half) and Fuller Street

  • Storm installation and sanitary sewer manhole replacement is scheduled to continue during the week of 9/20. Lane and / or road closures are anticipated on W. 54th St. Expect limited access to other Phase 2 roads and driveways for short periods. The contractor will knock on your front door to notify you of the driveway access restrictions.
  • Watermain improvements on Fuller St adjacent to the France Avenue intersection and partial watermain improvements on Abbott Place are complete.
  • Water service replacements are scheduled to be complete by 9/17.


US Internet

US Internet plans to install fiber optic lines in the City right of way beginning in late September. More details can be found here.


Parking restrictions remain in effect for Phase 1 and 2. There is No Parking from the hours of 7 AM to 9 PM or until the contractor has noticeably left for the day. Please remember these schedules are weather-dependent and are subject to change.