Construction Update 9/2/2021

Phase 1

  • Installation of concrete aprons and driveways is complete. Expect access to your driveways on or before Saturday 9/4.
  • Sanitary sewer lining continues. See the link for details.
  • The first layer of asphalt paving is scheduled to occur late during the week of 9/6.
  • Parking restrictions remain in effect for Phase 1. There is No Parking from the hours of 7 AM to 9 PM or until the contractor has noticeably left for the day.


Phase 2

  • Asphalt pavement reclamation is scheduled to occur mid week during the week of 9/6. This process grinds up the pavement and gravel underneath the road to produce a suitable recycled material to use as a temporary driving surface.
  • Replacement of deteriorating sanitary sewer manholes is scheduled to begin during the week of 9/6. At select locations, you can expect limited access to your driveway for short periods while the contractor replaces the manholes. The contractor will knock on your front door to notify you of the driveway access restriction.
  • Watermain service installation and storm sewer installation is scheduled to begin during the week of 9/6. Expect water shutoff and limited access to some roads and driveways for short periods. The contractor will knock on your front door to notify you of the temporary water shutoff and driveway access restrictions.
  • Mail delivery for Abbott Place residents to a temporary cluster box located on W 54th St between Beard Avenue and Abbott Place is scheduled to begin on Tuesday 9/7. Please check your mail for this important notice from the post office for more details.
  • Parking restrictions will be in effect for Phase 2 starting the week of 9/6. There is No Parking from the hours of 7 AM to 9 PM or until the contractor has noticeably left for the day.


US Internet

US Internet plans to install fiber optic lines in the City right of way beginning in late September. More details can be found here.