Construction Update 10/1/2021

Phase 1 (West 55th Street, Beard Avenue (south half), Beard Court, Drew Avenue (south half) and Ewing Circle

  • Irrigation system repairs began on 9/24 and are scheduled to continue during the week of 10/4.
  • Topsoil installation began. Seeding and hydromulching will begin during the week of 10/4.


Phase 2 (West 54th Street, Abbott Place, Beard Avenue (north half), Drew Avenue (north half) and Fuller Street

  • Utility installation is complete.
  • Roadway excavation began on Fuller Street and will continue during the week of 10/4. The contractor will remove at least 1 foot of soil below the current road surface for the full width of the street to install the gravel base and confirm the soils are stable enough to support vehicular traffic. During this work, you can expect periodic loss of access to your driveways for up to an hour. If you need immediate access, please wave to one of the contractors to get their attention and they can accommodate. Lane and / or road closures are anticipated on W. 54th St during the week of 10/4.


US Internet

US Internet plans to install fiber optic lines in the City right of way beginning in October. More details can be found here.


Parking restrictions remain in effect for Phase 1 and 2. There is No Parking from the hours of 7 AM to 9 PM or until the contractor has noticeably left for the day. Please remember these schedules are weather-dependent and are subject to change