Update

In the last month we've installed shoring and dug a big hole. At the bottom we've started to install forms.

In the next month we'll be pouring a concrete rectangle with a 'cutting edge' that will create the deepest part of the station. We'll set up a crane and begin excavating the middle of the concrete rectangle to sink the cutting edge.