Update

In the last month we've finished sinking the caisson. The final depth was within 0.02 feet of the planned depth and a bottom concrete seal has been poured. Northern Dewatering has set up point wells around the new wet well and has begun dewatering to allow for access to bottom to begin pouring the floor slab and wet well divider wall that will split the space into two wet wells.