Update

Since the last update we've hit a snag, the dewatering took longer than anticipated but the contractor worked to install a piezometer and more pumps to pull the water level down while watching the pressure so that the base slab could be poured. Magney construction is forming up the final pour for the wet well to bring the structure up to the planned grade in the next week. In the month ahead the project will be moving into the road with rolling road closures of the intersections of Claremore/Oaklawn/72nd and 72nd/Cornelia.