Construction Update 10/15/2021

Phase 2:

  • The final asphalt layer will be paved the week of 10/18. Check your front door daily for a notification on this work.


Phase 3:

  • Concrete driveway aprons and concrete driveway replacements are in progress on Code Ave, W 57th St, and part of Melody Lake Drive. These blocks are scheduled to have the first layer of asphalt paved on 10/15.
  • The concrete curb and gutter installation for the remainder of phase 3 streets is now scheduled for early in the week of 10/18.
  • After the curb is installed, crews will begin grading the boulevards for topsoil placement.
  • Topsoil placement on Dale Ave and Bernard Pl is complete and topsoil work will transition to the remainder of the phase after the concrete has cured.


Phase 4:

  • The sidewalk excavation between Code Ave and the Frontage Road is still anticipated to begin the week of 10/18.
  • During the sidewalk grading, crews will be preparing the boulevards for topsoil placement.
  • The remainder of the curb and gutter installation is now scheduled for early in the week of 10/18. The concrete driveway aprons and concrete driveway replacements will follow the curb and gutter installation.


Phase 5:

  • Storm sewer installation is anticipated to be complete before 10/19.
  • Street excavation continues on Hansen Rd, and is expected to be complete on 10/22.
  • Concrete curb and gutter installation will follow the street excavation, and is scheduled for late in the week of 10/18.
Share Construction Update 10/15/2021 on Facebook Share Construction Update 10/15/2021 on Twitter Share Construction Update 10/15/2021 on Linkedin Email Construction Update 10/15/2021 link

Consultation has concluded