Phase 1

  • The final asphalt layer on Hansen Road is scheduled to be paved on Saturday, 10/23. Check your front door daily for a notification on this work.


Phase 2:

  • The final asphalt layer is scheduled to be paved on Saturday, 10/23. Check your front door daily for a notification on this work.


Phase 3:

  • The concrete curb and gutter installation for the remainder of the streets is scheduled for 10/20 and 10/21.
  • Concrete aprons and concrete driveway replacements are scheduled to resume on Saturday, 10/23 and continue into the week of 10/25.
  • After the curb is installed, crews will begin grading the boulevards for topsoil placement.


Phase 4:

  • The remainder of the concrete curb and gutter installation is now scheduled for 10/21. The driveway aprons, concrete driveway replacements, and sidewalk will follow the curb and gutter installation.
  • Boulevard excavation for sidewalk installation between Code Ave and the Frontage Road is scheduled to begin on 10/22. The driveway removal limits have been marked and saw cut.
  • During the sidewalk grading, crews will be preparing the boulevards for topsoil placement.


Phase 5:

  • Hansen Rd street excavation is expected to conclude on 10/22.
  • Concrete curb and gutter installation will follow the curb installation in phases 3 and 4, and may begin on portions of Hansen Rd as soon as 10/21.


Phase 6

  • Road reconstruction on Windsor Ave has been postponed for 2021. Work will resume in spring 2022. Stay tuned for a door notification on the subject.


Phases 3-5

  • In lieu of dormant seeding this fall, the contractor may only place stabilizing hydromulch on the topsoil this fall and place seed in spring 2022. Stay tuned for updates.