Construction Update 10/28/2021

Phase 3:

  • Concrete driveway apron installation is complete throughout the phase.
  • The first layer of asphalt will be placed on the remaining streets the week of 11/1.
  • The contractor will continue to prepare the boulevards for topsoil placement throughout the phase.
  • Topsoil placement is scheduled to continue on 11/3.


Phase 4:

  • Concrete work is scheduled to resume in the phase on 10/29, including driveways and sidewalk.
  • Excavation and installation of gravel base for the concrete sidewalk is complete between Code Ave and Normandale. Crews will prepare the boulevards for topsoil placement prior to concrete installation, which is scheduled for the week of 11/1.


Phase 5:

  • Concrete curb and gutter installation is scheduled to finish on 10/29.
  • Concrete driveway aprons and concrete driveway replacements are scheduled to begin on 10/29.
  • After the concrete work concludes, crews will begin preparing the boulevards for topsoil placement.


Phases 3-5

  • In lieu of dormant seeding this fall, the contractor may only place stabilizing hydromulch on the topsoil this fall and place seed in spring 2022. Stay tuned for updates.
Share Construction Update 10/28/2021 on Facebook Share Construction Update 10/28/2021 on Twitter Share Construction Update 10/28/2021 on Linkedin Email Construction Update 10/28/2021 link

Consultation has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>