Construction Update 11/12/2021

Phase 2:

  • The final layer of asphalt pavement on the remaining portions of Grove Street has been rescheduled for Monday, 11/15 (weather permitting).


Phase 3:

  • The contractor will apply hydromulch to the topsoil throughout the phase during the week of 11/15.
  • The final layer of asphalt pavement has been rescheduled for Monday, 11/15 (weather permitting).


Phase 4:

  • Topsoil placement is scheduled to resume Monday, 11/15.
  • The contractor will apply hydromulch to the topsoil throughout the phase the week of 11/15.


Phase 5:

  • The first layer of asphalt pavement will be complete on 11/12.
  • Topsoil placement will begin the week of 11/15.
  • Mailbox reinstallations will occur during the week of 11/15.
  • Asphalt driveway patching is expected to begin on 11/15.
  • The final layer of asphalt pavement is scheduled to be installed late in the week of 11/15.


All Phases

The Contractor will begin sawing and sealing the asphalt pavement beginning the week of 11/15 in Phase 1. This process provides room for the asphalt to expand and contract during the freeze thaw cycle. This work is anticipated to take a few hours per block, and will continue in each phase after the final asphalt layer is placed.



Share Construction Update 11/12/2021 on Facebook Share Construction Update 11/12/2021 on Twitter Share Construction Update 11/12/2021 on Linkedin Email Construction Update 11/12/2021 link

Consultation has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>