Construction Update 11/12/2021
Phase 2:
- The final layer of asphalt pavement on the remaining portions of Grove Street has been rescheduled for Monday, 11/15 (weather permitting).
Phase 3:
- The contractor will apply hydromulch to the topsoil throughout the phase during the week of 11/15.
- The final layer of asphalt pavement has been rescheduled for Monday, 11/15 (weather permitting).
Phase 4:
- Topsoil placement is scheduled to resume Monday, 11/15.
- The contractor will apply hydromulch to the topsoil throughout the phase the week of 11/15.
Phase 5:
- The first layer of asphalt pavement will be complete on 11/12.
- Topsoil placement will begin the week of 11/15.
- Mailbox reinstallations will occur during the week of 11/15.
- Asphalt driveway patching is expected to begin on 11/15.
- The final layer of asphalt pavement is scheduled to be installed late in the week of 11/15.
All Phases
The Contractor will begin sawing and sealing the asphalt pavement beginning the week of 11/15 in Phase 1. This process provides room for the asphalt to expand and contract during the freeze thaw cycle. This work is anticipated to take a few hours per block, and will continue in each phase after the final asphalt layer is placed.
Share Construction Update 11/12/2021 on Facebook
Share Construction Update 11/12/2021 on Twitter
Share Construction Update 11/12/2021 on Linkedin
Email Construction Update 11/12/2021 link
Consultation has concluded