Construction Update 11/17/2021

Phase 3:

  • The contractor will apply hydromulch to the topsoil throughout the phase the week of 11/15.


Phase 4:

  • The final layer of asphalt pavement is scheduled to be installed on 11/19.
  • The contractor will apply hydromulch to the topsoil throughout the phase the week of 11/15.


Phase 5:

  • Mailbox reinstallations are in progress on Hansen Road.
  • The final layer of asphalt pavement is scheduled to be installed on 11/19.
  • Topsoil placement is complete in the phase, the contractor will apply hydromulch to the topsoil the remainder of the week.