Construction Update 11/17/2021
Phase 3:
- The contractor will apply hydromulch to the topsoil throughout the phase the week of 11/15.
Phase 4:
- The final layer of asphalt pavement is scheduled to be installed on 11/19.
- The contractor will apply hydromulch to the topsoil throughout the phase the week of 11/15.
Phase 5:
- Mailbox reinstallations are in progress on Hansen Road.
- The final layer of asphalt pavement is scheduled to be installed on 11/19.
- Topsoil placement is complete in the phase, the contractor will apply hydromulch to the topsoil the remainder of the week.