Construction Update 11/5/2021

Phase 2:

  • The final layer of asphalt pavement is scheduled on the remaining portions of Grove Street late in the week of 11/8.


Phase 3:

  • Topsoil placement will resume on the remaining streets on 11/10.
  • The contractor will apply hydromulch to the topsoil throughout the phase the week of 11/15.
  • The final layer of asphalt pavement is scheduled for late in the week of 11/8.


Phase 4:

  • Concrete sidewalk placement is scheduled to be complete on 11/5.
  • Topsoil placement will resume the week of 11/8.
  • The contractor will apply hydromulch to the topsoil throughout the phase the week of 11/15.


Phase 5:

  • Concrete driveway aprons and concrete driveway replacements are complete.
  • The sidewalk installation continues, and as anticipated to be complete by 11/10.
  • The first layer of asphalt pavement is scheduled for late in the week of 11/8.


Phases 3-5

  • In lieu of dormant seeding this fall, the contractor will only place stabilizing hydromulch on the topsoil this fall and place seed in spring 2022.


Share Construction Update 11/5/2021 on Facebook Share Construction Update 11/5/2021 on Twitter Share Construction Update 11/5/2021 on Linkedin Email Construction Update 11/5/2021 link

Consultation has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>