Construction Update 11/5/2021
Phase 2:
- The final layer of asphalt pavement is scheduled on the remaining portions of Grove Street late in the week of 11/8.
Phase 3:
- Topsoil placement will resume on the remaining streets on 11/10.
- The contractor will apply hydromulch to the topsoil throughout the phase the week of 11/15.
- The final layer of asphalt pavement is scheduled for late in the week of 11/8.
Phase 4:
- Concrete sidewalk placement is scheduled to be complete on 11/5.
- Topsoil placement will resume the week of 11/8.
- The contractor will apply hydromulch to the topsoil throughout the phase the week of 11/15.
Phase 5:
- Concrete driveway aprons and concrete driveway replacements are complete.
- The sidewalk installation continues, and as anticipated to be complete by 11/10.
- The first layer of asphalt pavement is scheduled for late in the week of 11/8.
Phases 3-5
- In lieu of dormant seeding this fall, the contractor will only place stabilizing hydromulch on the topsoil this fall and place seed in spring 2022.
Share Construction Update 11/5/2021 on Facebook
Share Construction Update 11/5/2021 on Twitter
Share Construction Update 11/5/2021 on Linkedin
Email Construction Update 11/5/2021 link
Consultation has concluded