Construction Update - Windsor Ave - 4/22/22
Windsor Ave
- Valley Paving is scheduled to begin removing curb and gutter as well as reclaim the asphalt pavement into a gravel driving surface on 4/25.
- Kusske Construction will begin connecting homes to the temporary water service on 4/25. If you aren’t typically home during working hours, check your front door daily for a notice from Kusske Construction regarding scheduling your temporary water hookup.
- Once homes are connected to the temporary watermain, the new watermain installation will begin. The new watermain installation is anticipated to conclude during the week of 5/2.