Construction Update 5/20/2021

Please remember to check your front door daily for time sensitive information and that schedules are weather dependent.

Phase 1:

  • The contractor is expected to begin excavating the road surface on 5/21. The contractor will remove soils to a depth of 1 - 3 feet below the current road surface for the full width of the street to install the gravel base and confirm the soils are stable enough to support vehicular traffic. During this work, you can expect periodic loss of access to your driveways for up to an hour. If you need immediate access, please wave to one of the contractors to get their attention and they can accommodate. Road excavation work is expected to continue through the week of 6/7.
  • Water service installations are expected to be complete by 5/25. Following completion, the contractor will connect houses to the new watermain and remove the temporary water system.
  • Storm sewer and sump drain installation is expected to start on 5/21 and last through 5/28.

Phase 2:

  • Parking restrictions are in effect. There is No Parking from the hours of 7 AM to 9 PM (or until the contractor has noticeably left for the day).
  • The contractor has begun reclaiming a portion of the asphalt pavement, which grinds up the pavement and gravel underneath the road to produce a suitable recycled material to use as a temporary driving surface. Removal of concrete curb and the end of your driveway pavement will also likely occur, as will trees identified for removal.
  • The week of 5/24 Kusske Construction will begin installing a temporary above ground water supply system. This will allow the contractor to replace the existing watermain and services with minimal disruption to your water supply. Please check your front door soon for more information regarding the contractor connecting your home to the temporary water service.
Share Construction Update 5/20/2021 on Facebook Share Construction Update 5/20/2021 on Twitter Share Construction Update 5/20/2021 on Linkedin Email Construction Update 5/20/2021 link

Consultation has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>