Construction Update 5/27/2021

Phase 1:

  • Road excavation work is ongoing and is now expected to wrap up the week of 6/14 due to several rain days.
  • Water service installation is complete, and the temporary water system will soon be removed.
  • Sump drain installation is in progress, and storm sewer installation is expected to start on 5/28 and last through 6/4.



Phase 2:

  • The installation of a temporary above ground watermain will be complete by the end of the day 5/28. This will allow the contractor to replace the existing watermain and services with minimal disruption to your water supply. The contractor will need access to your basement to finalize this setup. You will be contacted by Kusske Construction Company by either a knock on the door or a notification on your front door. After the new watermain has been installed, they will reconnect your water service to the new watermain.
  • Watermain work is scheduled to start the week of 6/7, and the watermain and water service work is expected to finish in mid-June, weather permitting.


Have a happy and safe Memorial Day Weekend!

Share Construction Update 5/27/2021 on Facebook Share Construction Update 5/27/2021 on Twitter Share Construction Update 5/27/2021 on Linkedin Email Construction Update 5/27/2021 link

Consultation has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>