Construction Update 6/10/2021
Phase 1
- Underground utility installation for the phase is anticipated to be complete on 6/11.
- The roadway excavation and installation of gravel base is expected to be complete by 6/19.
- Concrete curb and gutter installation is scheduled to begin on 6/21, with concrete aprons/driveways beginning soon after. Check your front door daily for time sensitive notices.
Phase 2
- The above ground temporary watermain is online, and temporary water service connections are in progress.
- New watermain installation is scheduled to begin on 6/11. Complete of the watermain and service installations are expected by late June.
Phase 3
- Removals related to the temporary watermain installation are expected to start the week of 6/21.
All Phases
- The sanitary sewer lining contractor, Hydro-Klean, is on site cleaning and inspecting the condition of the City's sanitary sewer main throughout the project area. The sewer main lining schedule is to be determined.
- See the phasing map for reference.
Share Construction Update 6/10/2021 on Facebook
Share Construction Update 6/10/2021 on Twitter
Share Construction Update 6/10/2021 on Linkedin
Email Construction Update 6/10/2021 link
Consultation has concluded