Construction Update 6/10/2021

Phase 1

  • Underground utility installation for the phase is anticipated to be complete on 6/11.
  • The roadway excavation and installation of gravel base is expected to be complete by 6/19.
  • Concrete curb and gutter installation is scheduled to begin on 6/21, with concrete aprons/driveways beginning soon after. Check your front door daily for time sensitive notices.

Phase 2

  • The above ground temporary watermain is online, and temporary water service connections are in progress.
  • New watermain installation is scheduled to begin on 6/11. Complete of the watermain and service installations are expected by late June.

Phase 3

  • Removals related to the temporary watermain installation are expected to start the week of 6/21.

All Phases

  • The sanitary sewer lining contractor, Hydro-Klean, is on site cleaning and inspecting the condition of the City's sanitary sewer main throughout the project area. The sewer main lining schedule is to be determined.
  • See the phasing map for reference.