Construction Update 6/17/21

Phase 1

  • Utility installation is complete.
  • Due to a gas main removal delay with CenterPoint Energy, the roadway excavation is scheduled to be complete by 6/25.
  • Concrete crews were able to complete curb and gutter on Eastview Dr, Josephine Ave, and Hansen Rd. The remaining concrete driveways and aprons are scheduled to be poured on 6/21. Please check your front door for time sensitive notices.

Phase 2

  • Watermain installation will resume the week of 6/21. The remaining temporary water service connections will be made over the next 2 weeks.

Phase 3

  • Removals are still anticipated to start the week of 6/21.