Construction Update 6/24/21

Phase 1

  • Street Excavation is scheduled to be complete on 6/25.
  • Curb and gutter and concrete driveways are scheduled to be installed in early July. Check your front door daily for notices.
  • The first layer of asphalt pavement is scheduled for 6/28 along Josephine Ave, Eastview Dr, and Hansen Rd.

Phase 2

  • Watermain installation continues. The crews are expected to finish the watermain and water service installation the week of 7/12.

Phase 3

  • Removals related to the temporary watermain installation will continue over the next few weeks.

Phase 2, 3 and 4 - CenterPoint Energy Update

  • The City's contractor removed pavement in portions of phases 2-4 to allow for gas main removal by CenterPoint Energy’s contractor, Michels. You can expect limited access to your driveway for short periods while Michels removes the gas main. A representative from Michels will knock on your front door to notify you of driveway access restrictions.

Your patience so far this project is greatly appreciated. We'll do our best to minimize inconveniences.

Share Construction Update 6/24/21 on Facebook Share Construction Update 6/24/21 on Twitter Share Construction Update 6/24/21 on Linkedin Email Construction Update 6/24/21 link

Consultation has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>