Construction Update 6/4/2021
Phase 1:
- Sump drain and storm sewer installation is scheduled to be complete during the week of 6/7.
- The roadway excavation is scheduled to be complete by 6/19.
- Curb and gutter will follow the road excavation and is scheduled for the week of 6/21.
Phase 2:
- The above ground temporary watermain has been installed. Kusske Construction will be contacting you with a knock on the door or a notification on your door to set up temporary water service. Access your basement is necessary to finalize the water connection.
- The new watermain installation will begin the week of 6/7, and the watermain and service work is expected to finish in mid-June, weather permitting.