Construction Update 7/16/2021

Phase 1

  • The first layer of asphalt paving is complete phase wide.
  • Preparing the boulevards for topsoil placement is nearly complete. Topsoil installation is scheduled to begin 7/16 or 7/17.
  • Irrigation repairs continue.

Phase 2

  • New watermain installation is complete.
  • Water service installations are expected to be complete by 7/19. Following completion, the contractor will connect houses to the new watermain and remove the temporary water system.
  • Storm sewer and sump drain installation are scheduled to start the week of 7/19.
  • The contractor is expected to begin excavating the road surface on 7/20 on Code Ave. The contractor will remove soils to a depth of 1 - 3 feet below the current road surface for the full width of the street to install the gravel base and confirm the soils are stable enough to support vehicular traffic. During this work, you can expect periodic loss of access to your driveways for up to an hour. If you need immediate access, please wave to one of the contractors to get their attention and they can accommodate.
  • Concrete curb and gutter installation is scheduled to begin in late July / early August, with concrete aprons/driveways beginning soon after.

Phase 3

  • Michels continues removal of the old gas main.
  • Removals for temporary watermain are continuing throughout the phase.
  • Installation of the temporary above ground watermain will begin during the week of 7/19.
Share Construction Update 7/16/2021 on Facebook Share Construction Update 7/16/2021 on Twitter Share Construction Update 7/16/2021 on Linkedin Email Construction Update 7/16/2021 link

Consultation has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>