Construction Update 7/2/21

Phase 1

  • Concrete curb and gutter installation on remaining streets began on 7/1. Curb and gutter and concrete driveways are scheduled to continue through the week of 7/6.
  • The sidewalk on Hansen Rd is scheduled to be poured the week of 7/6.
  • Excavation for topsoil began on streets with the first layer of asphalt.
  • The irrigation contractor will request an appointment with impacted properties to repair damaged systems. Please check your front door for notification, including contractor contact information.


Phase 2

  • The watermain installation on Grove Street is complete. The remainder of the watermain installation will begin on 7/2, starting with W 58th St.
  • Water service installation will begin the week of 7/12. Check your front door daily for time sensitive notices, as you will likely lose access to your driveway temporarily while services are installed.


Phase 3

  • CenterPoint Energy's contractor Michels is removing the old gas main underneath the road surface.
  • Removals related to the temporary watermain installation will continue over the next few weeks.


Have a safe and happy Fourth of July!