Construction Update 7/22/2021

Benton Avenue Road Closure - Tuesday 7/27

  • Benton Avenue will be closed between Dale Ave and Bernard Pl on 7/27 for storm sewer and watermain work. Please see the posted detour route here. A 1 day closure is anticipated.

Phase 1

Topsoil installation is ongoing and is scheduled to be complete on 7/24.

  • Seeding and hydromulch is scheduled to begin on 7/28, but may be delayed until hot temperatures subside.
  • Minor landscaping items such as mulch and edging will occur as topsoil is installed.

Phase 2

  • Sump line and storm sewer installation is in progress and is scheduled to be complete the week of 7/26.
  • Roadway excavation began on 7/19. The contractor will remove soils to a depth of 1 - 3 feet below the current road surface for the full width of the street to install the gravel base and confirm the soils are stable enough to support vehicular traffic. During this work, you can expect periodic loss of access to your driveways for up to an hour. If you need immediate access, please wave to one of the contractors to get their attention and they can accommodate.
  • Concrete curb and gutter is scheduled to begin the week of 8/2, with concrete driveway installation to follow close behind.

Phase 3

  • The temporary watermain is being installed and sanitized throughout the phase. Kusske Construction will be contacting you with a knock on the door or a notification on your door to set up temporary water service. Access to your basement is necessary to finalize the water connection.
  • Watermain work is scheduled to start the week of 7/26.
Share Construction Update 7/22/2021 on Facebook Share Construction Update 7/22/2021 on Twitter Share Construction Update 7/22/2021 on Linkedin Email Construction Update 7/22/2021 link

Consultation has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>