Construction Update 7/29/2021

Phase 1

  • Seeding and hydromulch is scheduled to begin on 7/30. Stay tuned for a separate posting with tips to help grow green grass.
  • Landscape repairs including mulching and landscape edging continue. Plantings and tree replacements will installed at a later date.


Phase 2

  • Concrete Curb and Gutter and driveway installation will begin late during the week of 8/2. Look for a notice on your door with recommended parking locations during this work.
  • Storm sewer and sump line installation are scheduled to finish this week.
  • Street excavation continues and is expected to finish on 8/6.


Phase 3

  • The temporary above ground watermain is installed and sanitized. Temporary water service connections are ongoing by Kusske Construction and are expected to be complete on 7/30.
  • Watermain installation will begin on 7/30. You can expect periodic loss of access to your driveways for up to an hour during this work. If you need immediate access, please notify one of the onsite contractors and they can accommodate. Check your front door daily for time sensitive notices.
Share Construction Update 7/29/2021 on Facebook Share Construction Update 7/29/2021 on Twitter Share Construction Update 7/29/2021 on Linkedin Email Construction Update 7/29/2021 link