Construction Update 7/9/2021

Phase 1

  • Concrete work is scheduled to be complete on 7/9.
  • Preparing the boulevards for topsoil placement began. Topsoil installation is scheduled to begin the week of 7/12.
  • Bernard Pl, Code Ave, Tingdale Ave, and W 59th St are scheduled to receive the first layer of asphalt the week of 7/12.


Phase 2

  • New watermain installation is scheduled to be complete on 7/9.
  • Water service work began. You can expect periodic loss of driveway access while the new water service is installed, so check your front door daily for time sensitive notices.
  • Storm sewer and sump drain installation are scheduled to start the week of 7/12.


Phase 3

  • Michels continues removal of the old gas main.
  • Removals for temporary watermain are continuing throughout the phase.
  • Installation of the temporary above ground watermain will begin later during the week of 7/12.

Share Construction Update 7/9/2021 on Facebook Share Construction Update 7/9/2021 on Twitter Share Construction Update 7/9/2021 on Linkedin Email Construction Update 7/9/2021 link

Consultation has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>