Construction Update 7/9/2021
Phase 1
- Concrete work is scheduled to be complete on 7/9.
- Preparing the boulevards for topsoil placement began. Topsoil installation is scheduled to begin the week of 7/12.
- Bernard Pl, Code Ave, Tingdale Ave, and W 59th St are scheduled to receive the first layer of asphalt the week of 7/12.
Phase 2
- New watermain installation is scheduled to be complete on 7/9.
- Water service work began. You can expect periodic loss of driveway access while the new water service is installed, so check your front door daily for time sensitive notices.
- Storm sewer and sump drain installation are scheduled to start the week of 7/12.
Phase 3
- Michels continues removal of the old gas main.
- Removals for temporary watermain are continuing throughout the phase.
- Installation of the temporary above ground watermain will begin later during the week of 7/12.
Share Construction Update 7/9/2021 on Facebook
Share Construction Update 7/9/2021 on Twitter
Share Construction Update 7/9/2021 on Linkedin
Email Construction Update 7/9/2021 link
Consultation has concluded