Phase 1

  • Manhole castings and gate valves have been lifted to final grade.
  • Minor landscape repairs are still ongoing. Replacement plantings will occur later in the fall.


Phase 2

  • Curb and gutter installation is scheduled to resume on 8/13 and 8/14. Concrete driveway replacements are scheduled to continue the week of 8/16.
  • The first layer of asphalt paving is scheduled for 8/20.
  • After the first layer of asphalt is installed, the boulevards will be excavated for topsoil installation and irrigation repairs will begin.


Phase 3

  • Watermain installation is in progress and is scheduled to be complete on 8/20.
  • Water service replacements are in progress and are scheduled to last through the week of 8/23.
  • Storm Sewer and sump drain installation will begin the week of 8/23.


Phase 4

  • Removals for the installation of temporary above ground watermain will begin the week of 8/16.
Share Construction Update 8/13/2021 on Facebook Share Construction Update 8/13/2021 on Twitter Share Construction Update 8/13/2021 on Linkedin Email Construction Update 8/13/2021 link

Consultation has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>