Phase 1
- Manhole castings and gate valves have been lifted to final grade.
- Minor landscape repairs are still ongoing. Replacement plantings will occur later in the fall.
Phase 2
- Curb and gutter installation is scheduled to resume on 8/13 and 8/14. Concrete driveway replacements are scheduled to continue the week of 8/16.
- The first layer of asphalt paving is scheduled for 8/20.
- After the first layer of asphalt is installed, the boulevards will be excavated for topsoil installation and irrigation repairs will begin.
Phase 3
- Watermain installation is in progress and is scheduled to be complete on 8/20.
- Water service replacements are in progress and are scheduled to last through the week of 8/23.
- Storm Sewer and sump drain installation will begin the week of 8/23.
Phase 4
- Removals for the installation of temporary above ground watermain will begin the week of 8/16.
Share Construction Update 8/13/2021 on Facebook
Share Construction Update 8/13/2021 on Twitter
Share Construction Update 8/13/2021 on Linkedin
Email Construction Update 8/13/2021 link
Consultation has concluded