Construction Update 8/20/2021

Phase 1

  • The contractor will be reseeding areas with poor turf establishment towards the end of the week of 8/30.


Phase 2

  • Code Ave, Tingdale Ave, and W 58th St will receive the first layer of asphalt on 8/20. The remaining streets are scheduled to have the first layer of asphalt installed the week of 8/23.
  • Concrete curb and driveway replacements are substantially complete. A few sections on Grove St near Dale Ave will be completed after the temporary above ground watermain is removed in Phase 3 .
  • The contractor will begin preparing the boulevards for topsoil placement, including removing debris and soils to a 6" depth, and any grading required to blend the boulevards into the curb.
  • The irrigation contractor will begin making repairs to damaged systems the week of 8/23. Check your front door for a notice from the irrigation contractor.
  • Topsoil placement is scheduled to begin the week of 8/30.
  • Seed and hydromulch applications will follow the topsoil placement.


Phase 3

  • The new watermain installation is complete.
  • New water service installation work is ongoing and is scheduled to finish 8/27.
  • The storm sewer and sump drain installation is in progress and is expected to finish 9/3.
  • Street excavation is expected to begin the week of 8/23.
  • Concrete curb and gutter will follow street excavation, and a portion of Phase 3 curb is currently planned for late in the week of 8/30.


Phase 4

  • Removals for the temporary above ground watermain are complete.
  • Crews will begin setting up the temporary above ground watermain the week of 8/23.
  • Watermain work will begin the week of 8/30 and is expected to be complete on 9/4.
Share Construction Update 8/20/2021 on Facebook Share Construction Update 8/20/2021 on Twitter Share Construction Update 8/20/2021 on Linkedin Email Construction Update 8/20/2021 link

Consultation has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>