Construction Update 8/20/2021
Phase 1
- The contractor will be reseeding areas with poor turf establishment towards the end of the week of 8/30.
Phase 2
- Code Ave, Tingdale Ave, and W 58th St will receive the first layer of asphalt on 8/20. The remaining streets are scheduled to have the first layer of asphalt installed the week of 8/23.
- Concrete curb and driveway replacements are substantially complete. A few sections on Grove St near Dale Ave will be completed after the temporary above ground watermain is removed in Phase 3 .
- The contractor will begin preparing the boulevards for topsoil placement, including removing debris and soils to a 6" depth, and any grading required to blend the boulevards into the curb.
- The irrigation contractor will begin making repairs to damaged systems the week of 8/23. Check your front door for a notice from the irrigation contractor.
- Topsoil placement is scheduled to begin the week of 8/30.
- Seed and hydromulch applications will follow the topsoil placement.
Phase 3
- The new watermain installation is complete.
- New water service installation work is ongoing and is scheduled to finish 8/27.
- The storm sewer and sump drain installation is in progress and is expected to finish 9/3.
- Street excavation is expected to begin the week of 8/23.
- Concrete curb and gutter will follow street excavation, and a portion of Phase 3 curb is currently planned for late in the week of 8/30.
Phase 4
- Removals for the temporary above ground watermain are complete.
- Crews will begin setting up the temporary above ground watermain the week of 8/23.
- Watermain work will begin the week of 8/30 and is expected to be complete on 9/4.
Share Construction Update 8/20/2021 on Facebook