Road Closure & Construction Update - 8/26/2021

All dates are weather dependent and subject to change.

Hansen Road Closure (Phase 5):

  • Phase 5 is scheduled to begin on 8/30 with tree and other removals associated with the installation of a large modular block retaining wall on the west side of the 5700 block of Hansen Rd.
  • Both road and lane closures will occur beginning on Monday 8/30 for up to 10 weeks. The closures are required for the safe construction of the retaining wall and significant utility improvements. Traffic impacts include:
    • Hansen Road will be fully closed for both northbound and southbound traffic at the CP Railroad crossing.
    • Hansen Road will be closed to northbound traffic between Benton Ave and the CP Railroad crossing. One way southbound traffic will remain open.
    • Please follow the alternate route shown here.


Phase 2:

  • The first layer of asphalt is scheduled for installation on Grove St, Bernard Pl, and Dale Ave on 8/27.
  • The contractor will continue preparing the boulevards for topsoil placement.
  • The irrigation contractor began making repairs to damaged irrigation systems. Please check your front door for time sensitive information. The irrigation contractor will be leaving contact information to discuss the repairs.
  • Topsoil placement is scheduled for the week of 8/30.


Phase 3:

  • New water service installations are expected to be complete for by the end of the day 8/26.
  • Storm sewer and sump line installation is expected to be complete on 9/11.
  • Street Excavation is scheduled to begin on 8/26 for Dale Ave. The contractor will remove soils to a depth of 1 - 3 feet below the current road surface for the full width of the street to install the gravel base and confirm the soils are stable enough to support vehicular traffic. During this work, you can expect periodic loss of access to your driveways for up to an hour. If you need immediate access, please wave to one of the contractors to get their attention and they can accommodate.
  • Concrete curb and gutter installation is scheduled for Dale Ave and Bernard Pl starting 9/8.


Phase 4:

  • The temporary watermain installation is complete. Following sanitizing of the temporary system, Kusske Construction will be contacting you with a knock on the door or a notification on your door to set up temporary water service. Access to your basement is necessary to finalize the water connection.
  • The watermain installation is scheduled to occur the week of 8/30.



Share Road Closure & Construction Update - 8/26/2021 on Facebook Share Road Closure & Construction Update - 8/26/2021 on Twitter Share Road Closure & Construction Update - 8/26/2021 on Linkedin Email Road Closure & Construction Update - 8/26/2021 link

Consultation has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>