Construction Update 8/5/2021

Phase 1

  • The seeding and hydromulch application is complete. The contractor will be responsible for establishing the grass, including initial watering. However, residents are encouraged to assist during this period to help establish the turf more quickly. See the post titled “Tips for Growing Green Grass” or watch the video titled “Growing Green Grass”. Please note that any restrictions in place for watering should be observed.
  • Crews will begin raising manhole castings to their final height over the next few weeks.


Phase 2

  • Concrete Curb and Gutter installation is ongoing and will continue through the week of 8/9.
  • Concrete driveway replacements are in progress. Please note that you will lose access for up to 5 days while the concrete cures.
  • Street Excavation is scheduled to be complete on 8/6.
  • The first layer of asphalt is scheduled to be installed late in the week of 8/9.


Phase 3

  • Watermain installation began. Due to the geometry of Melody Ln, Melody Lake Dr, and Code, residents may lose driveway access while the new watermain is installed. Check your front door daily for time sensitive notices.
  • Water service replacements are scheduled to begin on Dale Ave on 8/9.


Phase 4

  • Removals for the temporary watermain are expected to start the week of 8/16 west of Code Avenue.
Share Construction Update 8/5/2021 on Facebook Share Construction Update 8/5/2021 on Twitter Share Construction Update 8/5/2021 on Linkedin Email Construction Update 8/5/2021 link

Consultation has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>